• home
  • posts
  • installing horizontal flow reedbed
  • Posted March 19th, 2016
    1

    Installing a horizontal-flow reedbed

    Installing a horizontal-flow reedbed

    This week we undertook the building of a ‘proper’ horizontal flow reedbed. Our existing little ones were a hastily built, stopgap measure that we installed when we got here, and it was time to do things correctly. A horizontal flow reedbed can cope with our greywater, which has been passed through a basic straw filter to remove large food particles.  We used washed stone and sand -2 tonne of stone, and about 3/4 tonne of sand. The reedbed is approximately 30cms deep, comprising mainly stone with a 50mm layer of sand at the top, and is planted with reedmace that were growing in wet spots around the site.

    DSCF4273-2

    Here is the system (illustration by Daniel). The build took us two and a half days, with a lot of time being spent on ensuring that the levels between the inlet and outlet were correct, so that the reedbed will always remain full of water to just below the surface.

    DSCF4198-2

    The area once the existing undergrowth was cleared.

    DSCF4203-2

    The old little (non-functioning) vertical reedbed and pipework are removed.

    DSCF4201-2

    The area between the new reedbed and the big pond being cleared by Daniel.

    DSCF4208-2

    A crucial bit – the soil is cleared to form the banks of the reedbed, and the bottom levelled to give a gentle 1:100 slope. Just off horizontal, basically.

    DSCF4216-2

    A test with some water to ensure that it does indeed head in the right direction before we put the proper liner in. It is crucial to get the slope right – you don’t want areas where the water settles and won’t flow through the reedbed and away.

    DSCF4219

    We put these pieces of 2″ pipe under the plastic layer to form baffles that would direct water at the bottom of the reedbed around, thus slowing it down.

    DSCF4222-2

    We used four layers of silage sheet in the absence of a ‘real’ pond liner.

    DSCF4227-2

    This was protected by used tonne builder’s bags to protect the plastic. Here Daniel is shovelling gravel onto them to keep them in place before the area is filled with gravel. We used nearly 2 tonne.

    DSCF4234-2

    The outlet is created by making a hole through the liner(s), taping the liner around the outlet pipe, and then using a clamp (one of those wall clamps used to hold soil pipe onto the side of a house), tightened to form a seal.

    DSCF4239-2

    The second layer of sealing is clay – placed both sides of the seal and worked in around the pipe.

    DSCF4240-2A couple of tiles and stones protect the outlet from blockage before being buried in stones.

    DSCF4244-2

    Now the reedbed is filled with stones to just below the level of the inlet, and Felix and Lyra test this by filling with water, and adjusting the stones level until it is even across the surface of the reedbed.

    DSCF4248-2

    The outlet effectively sets the level inside the reedbed, as more pipe can be added to raise the level before it overflows to the pond.

    DSCF4252-2

    Here the water level has come up and we are moving the gravel around to get a true level.

    DSCF4253-2

    And here is the completed outlet after some adjustments. Once the water in the reedbed reaches the correct level (ie just below the surface), it can overflow out to the pond, but the reedbed always remains full of water. The opening at the top allows for water sampling to be carried out.

    DSCF4256-2

    A layer of sand is added, and the planting of the reeds begins. We are using reedmace as it grows nearby, and is happy in our microclimate. Be sure to plant the reeds so that they are in the wet layer below the surface.

    DSCF4260-2

    Planting almost complete, and we are edging the reedbed with stones to conceal the plastic liner.

    DSCF4281

    This fitting causes the inlet water to spread out, reducing erosion in front of the pipe, and ensuring that water spreads out over the surface of the reedbed.

    DSCF4282

    Completed reedbed, after connection, and with the pipework mostly buried.


    The views expressed in our blog are those of the author and not necessarily lowimpact.org's


    1 Comment

    • 1Tina June 28th, 2017

      Fantastic information, and great photos, I feel a bit more confident to start my own now, thank you.


    Leave a comment

    We welcome questions.

    There’s a crash coming – a slap from Mother Nature. This isn’t pessimistic; it’s realistic.

    The human impact on nature and on each other is accelerating and needs systemic change to reverse.

    We’re not advocating poverty, or a hair-shirt existence. We advocate changes that will mean better lives for almost everyone.

    Sign up to our newsletter

    Facebook icon Twitter icon Youtube icon

    All rights reserved © lowimpact 2023